Center for Computing & Data Sciences – Construction Update – 9/18/20

Excavation continues at the tower

During the weekend of September 19th

  • On Saturday, crews will be on site to continue with the excavation in the tower portion of the building, along with the installation of bracing for the support of the excavation system.

During the week of September 21st

  • Excavation down to the 2nd level of bracing for the support of the excavation system continues in the tower portion of the building.
  • Installation of cross bracing members, for the support of the excavation system, continues as excavation progresses in the tower.
  • Formwork and rebar placement will begin for the structural mat slab in the podium.
  • During the week of September 28th, a large concrete pour (roughly 1,200 container yards and approximately 120 trucks) is anticipated to occur; additional information will be included in the next update.
  • Please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up-to-date information via these notifications.
Tower crane assembled on site last weekend

View all posts