During the week of June 29th

  • Installation of utility feeds, power, and water from Granby Street to the site will continue.
  • Driving of the sheeting for the Support of Excavation (SOE) system will continue along the north (Bay State Road Brownstones) south (Commonwealth Avenue) and the west (Granby Street). All sheets at the east end of the site (Sargent College) have been completed.
  • At the mock-up (766 Commonwealth Avenue parking lot), installation of the façade panels and masonry products will be completed, along with sealants and final details prior to review by the project team and university leadership in the coming weeks.
  • As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up to date information via these notifications.
Installation of the sheets along the east edge of the site continues, parallel to Commonwealth Avenue
Various façade materials installed on the mock-up