Myles Standish Hall – Construction Activity – 9/9/17 – 9/15/17

Myles

For 9/9/17 to 9/15/17:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

 Saturday Work – 9/9/17

  • Coring – Floors 2-9
  • Exterior layout
  • Clean up and loadout – Bay State Road

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street

Roof Myles (Exterior)

  • Install parapet blocking
  • Coring and sawcutting

For questions, please contact Brian Kelley or visit our website for more information.