For 9/2/17 to 9/8/17:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday – 9/2/17 – No work

Monday – 9/4/17 – No work – Labor Day

Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street

Roof Myles (Exterior)

  • Install parapet blocking
  • Coring and sawcutting

 