Warren Towers Renovation Construction Update – 4/3/26

General Project Information

  • Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 9:00 a.m. to 5:00 p.m. (1st shift for work outside/adjacent to student rooms), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
  • The team is currently in the main renovation phase of the project.
  • Entering the jobsite: Authorized personnel only and no trespassing. Anyone wishing to enter the site must sign in at the construction office, observe and comply with all posted signage and personnel protective equipment requirements.
  • Emergency Contacts:
    • Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 4/4

Saturday & Sunday (1st and 2nd shift)

Exterior Work

Tower A

4th Floor Podium Roofs

  • Low roofs will be used as laydown areas for tools, supplies, and materials as the staging is getting disassembled.
  • Staging crews will be removing their material from the lower roof levels using a mobile crane.

East and West Facades

  • Sealing and caulking of windows and metal trim panels.
Pictured are the new windows.
  • Masons are working on punch list items and touchups identified by the design team.

Front Façade and on Commonwealth Avenue

  • Sealing and caulking of windows and metal trim panels.
  • Masons are working on punch list items and touchups identified by the design team.
  • Installation of new door opening on the sidewalk at the fire pump room.

Rear Façade and Back Alley

  • Steel stud framing of window openings and closing of the building access leave out sections.
  • Installation of windows and metal trim along with caulking.
  • Masons will continue with exterior brick veneer restoration work, selective demolition, installation of restoration anchors, air, water, and vapor barriers, new lintels, flashings, and relieving angles.
  • Disassembly of the hoist way access bridge.

Upper Roof

  • Work on the emergency backup generator connections continues.
  • Work continues on constructing the new mechanical penthouse and emergency electric room.
  • Assembly and installation of the DOAS unit, piping, sheet metal ductwork, and electrical connections continue.
  • Installation of metal panel roof screen.

      Tower B

      North, South, East, and West Facades

      • Staging crews will continue assembling scaffolding on levels 5 through 18.
      Pictured is the progress on Tower B.

      West Podium Terrace

      • Assembly and installation of heat pumps and condensers, including piping and electrical connections, continues on the mechanical platform.
      • Carpenters are working on the acoustic roof screen assembly.

      Multipurpose Room Roof (Podium D)

      • Work continues on constructing the new boiler room.
      • Installation of new roofing system and parapets.

      Cummington Mall
      (In and around the fenced area)

      • Daily deliveries of tools, supplies, and materials will be received at the construction loading docks within the fenced area.
      • Two-car personnel and materials hoist way remains in operation.
        • (The elevator operators begin their safety checks and preventative maintenance on the hoistway daily at 6:00 AM)
      • Tower B hoist way bridge construction is ongoing.
      • Crane work lifting materials to the lower roofs.
      Pictured is the continuing crane work.

      Cummington Mall West

      • A mobile crane will be loading masonry supplies to the west terrace.
        • This will block access to the reserved and patient parking on Cummington Mall, which will be relocated to the area in front of 44 Cummington Mall.
      • BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.

      Hinsdale Mall

      • Crews are installing scaffolding on the east end of the building.
      • The Warren Towers garage (Lot K) will remain open.
      • Please watch for sidewalk closures, BUPD detail officers, cones, and observe posted signage.

        Interior Work

        Tower A

        • Rough-in of HVAC piping, electrical, fire alarm, plumbing, and sheet-metal ductwork is ongoing.
        • Pressure testing of mechanical piping and sheet metal ductwork.
        • Steel stud framing of interior partitions and soffits.
        • Installation of hollow metal door frames.
        • Application of spray fireproofing, expanding foam insulation, and firestopping continues.
        • New window installation continues.
        • Drywall installation and taping.
        • Plaster patching at columns and beams continues.
        • Stair handrail and riser alterations.
        • Prime and painting of walls, ceilings, soffits, doors, and door frames.
        Pictured is the progress of finishing the corridors.
        • Floor preparation, waterproofing, and tile installation are ongoing in the core bathrooms.
        • Flooring and base installations in student dorm rooms.
        • Wall tile installation in corridors.
        • Installation of doors, hardware, millwork, and accessories.
        Pictured are the bathroom finishes.
        • Installation of solid surface countertops, windowsills, and hand drier panels.
        • Modernization of the tower elevators by Otis Elevator Company continues Saturdays and Sundays.
        • Finalization of plumbing, electrical and mechanical.
        • Interior final cleaning is ongoing.
        Pictured is a typical student room.
        Pictured is another view of a typical student room.

                Dining Hall

                • Crews will be making drain connections in the new dining hall.

                  Parking Garage 

                  • Work continues in main electrical room.
                  • Electricians will continue running wiring, conduits, and electrical gear throughout the parking garage, 1st, 2nd, and 3rd levels.
                  • Installation and assembly of electrical gear continues.
                  • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                  • Installation of mechanical piping continues.
                  • Construction of the new fuel storage room is ongoing in the southeast basement level of the parking garage.
                  • MDF room construction continues.
                  • Concrete and steel structural repair work continues in the parking garage on the 1st, 2nd, and 3rd floors.
                  • Sprinkler work continues on all levels.
                  • Masons continue installing block walls in the new mechanical and electrical rooms.
                  • Operation of temporary heaters on level 3.
                  • Please watch for adjusted parking patterns, cones, and observe signage.

                                During the week of 4/6

                                 Crews working 1st, 2nd & 3rd shifts

                                Exterior Work

                                Tower A

                                4th Floor Podium Roofs

                                • Low roofs will be used as lay down areas for tools, supplies, materials as the staging is getting disassembled.
                                • Staging crews will be removing their material off of the lower roof levels using a mobile crane.

                                East and West Facades

                                • Sealing and caulking of metal panels and windows continues.
                                • Masons are working on punch list items and touchups identified by the design team.

                                Front Façade and on Commonwealth Avenue

                                • Sealing and caulking of metal panels and windows continues.
                                • Masons are working on punch list items and touchups identified by the design team.
                                • Installation of new door opening on the sidewalk at the fire pump room on the street level.

                                Rear Façade and Back Alley

                                • Steel stud framing of window openings and closing up of the building access leave out sections.
                                • Installation of windows and metal trim, along with caulking.
                                • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
                                • Disassembly of the hoist way access bridge.

                                Upper Roof

                                Pictured are the MultiStack piping connections.
                                • Work continues constructing the mechanical penthouse and emergency electric room.
                                • Assembly and installation of DOAS units, piping, sheet metal ductwork, and electrical connections continue.
                                • Work on the emergency generator connections continues.
                                • Installation of metal panel roof screen.
                                Pictured is the roof of Tower A.

                                  Tower B

                                  North, South, East, and West Facades

                                  • Scaffolding installation continues on all façades.
                                  Pictured is the Tower B staging.

                                  West Podium Terrace

                                  • Assembly and installation of heat pumps and condensers continue, along with piping and electrical connections.
                                  • Carpenters will be working on the roof screen assembly.
                                  • Masons are installing block veneer.
                                  Pictured is the West Terrace.

                                    Multipurpose Room Roof (Podium D)

                                    • Work continues constructing the new boiler room.
                                    • Installation of new roofing system and parapets.

                                    Cummington Mall
                                    (In and around the fenced area)

                                    • Daily deliveries of tools, supplies, and materials will continue.
                                    • Crane work lifting materials to the lower roofs.
                                    • Two-car personnel and materials hoist way remains in operation.
                                      • (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.).
                                    • Temporary elevator hoist way and bridge beam assembly for Tower B continues and impacts two entry/exit doors at 111 Cummington Mall.

                                    Cummington Mall West

                                    • BUPD detail officers and construction staff will be on-site.

                                    Hinsdale Mall

                                    • Crews are installing scaffolding on the east end of the building.
                                    • Watch for sidewalk closures, BUPD detail officers, cones, and observe signage.

                                    Interior Work

                                    Tower A

                                    • Rough-in of HVAC piping, electrical, fire alarm, plumbing and sheet metal ductwork is ongoing.
                                    • Pressure testing of mechanical piping and sheet metal ductwork continues.
                                    • Steel stud framing of interior partitions and soffits continues.
                                    • Installation of hollow metal door frames continues.
                                    • Fireproofing and firestopping continues.
                                    • New window installation continues.
                                    • Drywall installation and taping continue.
                                    • Plaster patching continues.
                                    • Stair handrail and riser alterations continue.
                                    • Priming and painting of walls, ceilings, soffits, doors, and door frames continues.
                                    Pictured is the student lounge.
                                    Pictured is another view of the student lounge.
                                    • Floor preparation, waterproofing, and tile installation is ongoing in the core bathrooms.
                                    • Flooring and base installation begins in the student dorm rooms.
                                    • Wall tile installation in the corridors begins.
                                    Pictured are the toilet room accessories.
                                    • Installation of doors and hardware, and millwork begins.
                                    • Installation of solid surface countertops, windowsills, and hand drier panels.
                                    • Otis elevator modernization continues.
                                    • Finalization of plumbing, electrical, and mechanical.
                                    • Interior final cleaning is ongoing.
                                    • Third-party inspectors remain onsite as needed.

                                                Dining Hall

                                                • Crews will be making drain connections.

                                                  Parking Garage

                                                  • Work continues in the main electrical room.
                                                  Pictured is the main electrical room.
                                                  • Electricians will continue running wiring and conduits throughout the parking garage on levels 1 through 3.
                                                  • Installation of electrical gear continues.
                                                  • Plumbers will continue installing new water and drain lines in the basement and levels 1 through 3.
                                                  • Mechanical piping installation continues.
                                                  • Fuel storage room construction continues.
                                                  • MDF room construction continues.
                                                  • Concrete and steel structural repair work continues on levels 1 through 3.
                                                  • Work on sprinklers continues.
                                                  • Masons will continue installing block walls in the new mechanical and electric rooms.
                                                  • Temporary heaters remain in operation on Level 3.
                                                  • Please watch for adjusted parking patterns, BUPD detail officers, cones, and observe signage.

                                                                  Future / Notable Tasks

                                                                  • Continue performing FM global roof uplift testing on all roofs.
                                                                  • Fire pump delivery to the site in April.
                                                                  • Dining hall renovation begins on 5/9.
                                                                  • Escalator replacement starts on 5/19.
                                                                  • Tower B demolition begins 5/18.
                                                                  • Eversource to energize new electrical service
                                                                  • Furniture delivery and installation.