Warren Towers Renovation Construction Update – 3/20/26

General Project Information

  • Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 9:00 a.m. to 5:00 p.m. (1st shift for work outside/adjacent to student rooms), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the weekend of 3/21 & 3/22

Saturday & Sunday (1st and 2nd shift)

Exterior Work

Tower A

4th Floor Podium Roofs

  • Low roofs will be used as laydown areas for tools, supplies, and materials as the staging is getting disassembled.
  • Staging crews will be removing their material off of the lower roof levels using a mobile crane.

East & West Facades

  • Sealing and caulking of windows and metal trim panels.
  • Masons are working on punch list items and touchups identified by the design team.

Front Façade and on Commonwealth Ave.

  • Sealing and caulking of windows and metal trim panels
  • Masons are working on punch list items and touchups identified by the design team.
  • Installation of new door opening on the sidewalk at the fire pump room.

Rear Façade and Back Alley

  • Steel stud framing of window openings and closing up of the building access leave out sections.
  • Installation of windows and metal trim along with caulking.
  • Masons will continue with exterior brick veneer restoration work, selective demolition, installation of restoration anchors, air, water, and vapor barriers, new lintels, flashings, and relieving angles.
  • Disassembly of the hoist way access bridge.

Upper Roof

  • Work on the emergency backup generator connections continues.
  • Work continues on constructing the new mechanical penthouse and emergency electric room.
  • Assembly and installation of the DOAS unit, piping, sheet metal ductwork, and electrical connections continue.
  • Installation of metal panel roof screen.

      Tower B

      North, South, East, and West Facades

      • Staging crews will continue assembling scaffolding on levels 5 through 18.
      Pictured is the Tower B hoist way and bridge.

      West Podium Terrace

      • Assembly and installation of heat pumps and condensers, including piping and electrical connections, continues on the mechanical platform.
      • Carpenters are working on the acoustic roof screen assembly.

      Multipurpose Room Roof (Podium D)

      • Work continues on constructing the new boiler room.

      Cummington Mall
      (In and around the fenced area)

      • Daily deliveries of tools, supplies, and materials will be received at the construction loading docks within the fenced area.
      • Two-car personnel and materials hoist way remains in operation.
        • (The elevator operators begin their safety checks and preventative maintenance on the hoistway daily at 6:00 AM)
      • Tower B hoist way bridge construction is ongoing.

      Cummington Mall West

      • BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.

      Hinsdale Mall

      • Crews are installing scaffolding on the east end of the building.
      • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage.

      Commonwealth Avenue

      • Installation of an entry door at the fire pump room.

      Interior Work

      Tower A

      • Rough-in of HVAC piping, electrical, fire alarm, plumbing, and sheet-metal ductwork is ongoing.
      Pictured are the heating and cooling valance units in student rooms.
      • Pressure testing of mechanical piping and sheet metal ductwork.
      • Steel stud framing of interior partitions and soffits.
      • Installation of hollow metal door frames.
      • Application of spray fireproofing, expanding foam insulation, and firestopping continues.
      • New window installation continues.
      • Drywall installation and taping.
      • Plaster patching at columns and beams continues.
      • Stair handrail and riser alterations.
      • Prime and painting of walls, ceilings, soffits, doors, and door frames.
      • Floor preparation, waterproofing, and tile installation are ongoing in the core bathrooms.
        Pictured is the floor preparations in the bathrooms.
        • Flooring and base installations in student dorm rooms.
        • Wall tile installation in corridors.
        • Installation of doors, hardware, and millwork.
        Pictured is the millwork in the student lounge.
        • Installation of solid surface countertops, windowsills, and hand drier panels.
        • Modernization of the tower elevators by Otis Elevator Company continues Saturdays and Sundays.
        • Finalization of plumbing, electrical and mechanical.
        Pictured is the solid surface counter tops in the bathroom

        Dining Hall

        • Crews will be making drain connections.

          Parking Garage 

          • Work continues in main electrical room.
          Pictured is the progress on the main electrical room
          • Electricians will continue running wiring, conduits, and electrical gear throughout the parking garage, 1st, 2nd, and 3rd levels.
          • Installation and assembly of electrical gear continues.
          • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
          • Installation of mechanical piping continues.
          • Construction of the new fuel storage room is ongoing in the southeast basement level of the parking garage.
          • MDF room construction continues.
          • Concrete and steel structural repair work continues in the parking garage on the 1st, 2nd, and 3rd floors.
          • Sprinkler work continues on the basement and Levels 1 through 3.
          • Masons continue installing block walls in the new mechanical and electrical rooms.
          • Operation of temporary heaters on level 3.
          • Please watch for adjusted parking patterns, cones, and observe signage.

                  During the week of 3/23

                   Crews working 1st, 2nd & 3rd shifts

                  Exterior Work

                  Tower A

                  4th Floor Podium Roofs

                  • Low roofs will be used as lay down areas for tools, supplies, materials as the staging is getting disassembled.
                  • Staging crews will be removing their material off of the lower roof levels using a mobile crane.

                  East & West Facades

                  • Caulking of metal panels and windows continues.
                  • Masons are working on punch list items and touchups identified by the design team.

                  Front Façade and on Commonwealth Avenue

                  • Caulking of metal panels and windows continues.
                  • Masons are working on punch list items and touchups identified by the design team.
                  • Installation of new door opening on the sidewalk at the fire pump room on the street level.

                  Rear Façade and Back Alley

                  • Steel stud framing of window openings and closing up of the building access leave out sections.
                  • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
                  • Installation of new windows and metal panels continues.
                  • Caulking of metal panels and windows continues.
                  • Disassembly of the hoist way access bridge.

                  Upper Roof

                  • Work continues constructing the mechanical penthouse and emergency electric room.
                  • Assembly and installation of DOAS units, piping, sheet metal ductwork, and electrical connections continue.
                  • Work on the emergency generator connections continues.
                  • Installation of metal panel roof screen.

                    Tower B

                    North, South, East, and West Facades

                    • Scaffolding installation continues on all façades.
                    Pictured is the progress photo of Tower B staging.

                    West Podium Terrace

                    • Assembly and installation of heat pumps and condensers continue.
                    • Carpenters will be working on the roof screen assembly.

                      Multipurpose Room Roof (Podium D)

                      • Work continues constructing the new boiler room.

                      Cummington Mall
                      (In and around the fenced area)

                      • Daily deliveries of tools, supplies, and materials will continue.
                      • Two-car personnel and materials hoist way remains in operation.
                        • (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.).
                      • Temporary elevator hoist way and bridge beam assembly for Tower B continues and impacts two entry/exit doors at 111 Cummington Mall.
                      Pictured is the view from Cummington Mall.

                      Cummington Mall West

                      • BUPD detail officers and construction staff will be on-site.

                      Hinsdale Mall

                      • Crews are installing scaffolding on the east end of the building.
                      • Watch for sidewalk closures, BUPD detail officers, cones, and observe signage.

                        Commonwealth Avenue

                        • Installation of an entry door at the fire pump room.

                        Interior Work

                        Tower A

                        • Rough-in of HVAC piping, electrical, fire alarm, plumbing and sheet metal ductwork is ongoing.
                        Pictured is the relocated fire alarm panels.
                        • Pressure testing of mechanical piping and sheet metal ductwork continues.
                        Pictured is the Tower A laundry room rough plumbing.
                        • Steel stud framing of interior partitions and soffits continues.
                        • Installation of hollow metal door frames continues.
                        • Fireproofing and firestopping continues.
                        Pictured is the spray-on fireproofing in the MDF room.
                        • New window installation continues.
                        • Drywall installation and taping continue.
                        Pictured is the progress of a typical corridor.
                        • Plaster patching continues.
                        • Stair handrail and riser alterations continue.
                        • Priming and painting of walls, ceilings, soffits, doors, and door frames continues.
                        • Floor preparation, waterproofing, and tile installation is ongoing in the core bathrooms.
                        Pictured is the accessible bathroom progress photo.
                        • Flooring and base installation begins in the student dorm rooms.
                        • Wall tile installation in the corridors begins.
                        • Installation of doors and hardware, and millwork begins.
                        • Installation of solid surface countertops, windowsills, and hand drier panels.
                        • Otis elevator modernization continues.
                        Pictured is the new elevator car in Tower A.
                        • Finalization of plumbing, electrical, and mechanical.
                        • Third-party inspectors remain onsite as needed.

                        Dining Hall

                        • Crews will be making drain connections.

                          Parking Garage

                          • Work continues in the main electrical room.
                          • Electricians will continue running wiring and conduits throughout the parking garage on levels 1 through 3.
                          • Installation of electrical gear continues.
                          • Plumbers will continue installing new water and drain lines in the basement and levels 1through 3.
                          • Mechanical piping installation continues.
                          • Parking & Transportation office construction continues.
                          • Fuel storage room construction continues.
                          • MDF room construction continues.
                          • Concrete and steel structural repair work continues on levels 1 through 3.
                          • Work on sprinklers continues.
                          • Masons will continue installing block walls in the new mechanical and electric rooms.
                          • Temporary heaters remain in operation on Level 3.
                          • Please watch for adjusted parking patterns, BUPD detail officers, cones, and observe signage.

                                      Future / Notable Tasks

                                      • Continue performing FM global roof uplift testing on all roofs.
                                      • Fire pump delivery to the site in April.
                                      • 1st furniture delivery 4/9.
                                      • Dining hall renovation begins on 5/9.
                                      • Escalator replacement starts on 5/19.