Warren Towers Renovation Construction Update – 2/6/2026

General Project Information

  • Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 9:00 a.m. to 5:00 p.m. (1st shift for work outside/adjacent to student rooms), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
  • The team is currently in the main renovation phase of the project.
  • Emergency Contacts:
    • Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the weekend of 2/7

Saturday 1:00 a.m. – 6 p.m. | Sunday (1st shift)  (2nd, 3rd shift – clearing snow and ice if needed)

Exterior Work

Tower A

4th Floor Podium Roofs

  • Low roofs will be used as laydown areas for tools, supplies, and materials.

East & West Facades

  • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.

Front Façade and on Commonwealth Ave.

  • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.

Rear Façade and Back Alley

  • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.

Upper Roof

  • A large crane will begin setting the emergency backup generator onto the roof of Tower A on Saturday.
Pictured is the area of the roof that will receive the generator.
  • Work continues constructing the new mechanical penthouse and emergency electric room.
  • Assembly and installation of the DOAS unit, piping, sheet metal ductwork, and electrical connections continue.

Tower B

North, south, east, and west facades

  • Staging crews will load the materials onto the lower roofs on Saturday with a crane.

West Podium Terrace

  • A crane will be lifting supplies and materials onto the mechanical platform on Saturday, starting at 9:00 a.m.
  • Assembly and installation of heat pumps and condensers, including piping and electrical connections, continues on the mechanical platform.

Multipurpose Room Roof (Podium D)

  • Work continues constructing the new boiler room.

Cummington Mall
(In and around the fenced area)

Pictured is the worksite from afar.
  • Daily deliveries of tools, supplies, and materials will be received at the construction loading docks within the fenced area.
  • Two-car personnel and materials hoist way remains in operation.
    • (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.)
  • Tower B hoist way bridge construction is ongoing.

Cummington Mall West

  • A crane will be set up in the street to hoist equipment to the west terrace roof.
  • BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.

Hinsdale Mall

  • A large crane will be set up in the street to hoist electrical equipment to the roof of Tower A.
Pictured is the crane on Hinsdale Street.
  • BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.

Interior Work

Tower A

  • Installation of structural steel clips, plates, kickers and beam penetrations continues.
  • Rough-in of HVAC piping, electrical, fire alarm, plumbing, and sheet metal ductwork continues.
Pictured are the valance unit connections.
  • Pressure testing of mechanical piping and sheet metal ductwork continues.
  • Steel stud framing of interior partitions and soffits continues.
  • Installation of hollow metal door frames continues.
  • Application of spray fireproofing, expanding foam insulation, and firestopping continues.
  • New window installation continues.
  • Drywall installation and taping continues.
Pictured is the bathroom progress.
  • Plaster patching at columns and beams continues.
  • Stair handrail and riser alterations are ongoing.
  • Priming and painting of walls, ceilings, soffits, doors, and door frames continues.
  • Floor and wall preparation and waterproofing is ongoing.
  • Installation of fire protection sprinkler risers, mains, branch lines, and heads continues.
  • Modernization of the Tower elevators by Otis Elevator Company continues.

        Parking Garage 

        • Electricians continue running wiring, conduits, and electrical gear throughout Levels 1–3.
        Pictured is the electrical vault room grounding bar.
        • Plumbers continue installing new water and drain lines in the basement and Levels 1–3.
        • Concrete and steel structural repairs continue on Levels 1–3.
        Pictured is the floor repair area in the garage.
        • Sprinkler work continues on basement and Levels 1–3.
        • Masons continue installing block walls in the new mechanical and electrical rooms.
        • Please watch for adjusted parking patterns, cones, and observe signage.

          During the week of 2/9

           Crews working 1st & 2nd shifts

          Exterior Work

          Tower A

          4th Floor Podium Roofs

          • Low roofs will be used as laydown areas for tools, supplies, materials, and temporary heating units.

          East & West Facades

          • Crews will be working on the low roofs east and west of Tower A.
          • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
          • Installation of new windows and metal panels continues.

          Front Façade and on Commonwealth Ave.

          • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
          • Installation of new windows and metal panels continues.
          Pictured are the north windows in Tower A.

          Rear Façade and Back Alley

          • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
          • Installation of new windows and metal panels continues.

          Upper Roof

          • Work continues constructing the mechanical penthouse and emergency electric room.
          • Assembly and installation of DOAS units, piping, sheet metal ductwork, and electrical connections continue.
          Pictured is the pressure and leak testing of the DOAS unit.
          • Installation work on the emergency generator continues.

          Tower B

          • Scaffolding installation continues on all façades. The crews will be working on levels 5-12 next week.
          Pictured is the worksite from afar.

          West Podium Terrace

          • Assembly and installation of heat pumps and condensers continue.
          • Piping and electrical connections on mechanical platforms continues.
          • Carpenters will be working on the roof screen assembly.
          Pictured is the west terrace progress photo.

            Multipurpose Room Roof (Podium D)

            • Work continues constructing the new boiler room.

            Cummington Mall
            (In and around the fenced area)

            • Daily deliveries of tools, supplies, and materials will continue.
            • Two-car personnel and materials hoist way remains in operation.
              • (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.).
            • Temporary elevator hoist way and bridge beam assembly for Tower B continues and impacts two entry/exit doors at 111 Cummington Mall.
            Pictured is the Tower B hoist way and bridge progress.

            Cummington Mall West / Hinsdale Mall

            • BUPD detail officers and construction staff will be on-site.

            Interior Work

            Tower A

            • Installation of structural steel clips, plates, kickers and beam penetrations is ongoing.
            • Rough-in of HVAC piping, electrical, fire alarm, plumbing and sheet metal ductwork is ongoing.
            • Pressure testing of mechanical piping and sheet metal ductwork continues.
            • Steel stud framing of interior partitions and soffits continues.
            • Installation of hollow metal door frames continues.
            • Fireproofing and firestopping continues.
            • New window installation continues.
            • Drywall installation and taping continue.
            • Plaster patching continues.
            • Stair handrail and riser alterations continue.
            • Priming and painting of walls, ceilings, soffits, doors, and door frames continues.
            • Floor and wall preparation and waterproofing is ongoing.
            Pictured is the floor preparation in progress.
            • Installation of wall and floor tile will begin.
            • Otis elevator modernization continues.
            • Third-party inspectors remain onsite as needed.

                Parking Garage

                • Work continues in the main electrical room.
                • Electricians will continue running wiring and conduits throughout the parking garage on levels 1-3.
                Pictured are the spools of wire ready to install.
                • Installation of electrical gear continues.
                • Plumbers will continue installing new water and drain lines in the basement and levels 1-3.
                • Mechanical piping installation continues.
                Pictured is the hot water heaters
                • Parking & Transportation office construction continues.
                • Fuel storage room construction continues.
                • Concrete and steel structural repair work continues on levels 1-3.
                • Work on sprinklers continues.
                • Masons will continue installing block walls in the new mechanical and electric rooms.
                • Temporary heaters remain in operation on Level 3.
                • Please watch for adjusted parking patterns, BUPD detail officers, cones, and observe signage.

                    Future / Notable Tasks

                    • Crane lift of mechanical equipment onto west terrace on 2/10.
                    • 1st delivery of interior doors and hardware on 2/11.
                    • Continuing window leak testing on Tower A.
                    • Continue performing FM Global Roof Uplift Testing on all roofs.