Warren Towers Renovation Construction Update – 1/16/2026
General Project Information
- Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 9:00 a.m. to 5:00 p.m. (1st shift for work outside/adjacent to student rooms), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
- The team is currently in the main renovation phase of the project.
- Emergency Contacts:
- Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
- Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758
During the weekend of 1/17–1/18
Saturday (1st shift) | No work planned on Sunday
Exterior Work
Tower A
4th Floor Podium Roofs
- Low roofs will be used as laydown areas for tools, supplies, and materials.
East & West Facades
- Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
Front Façade and on Commonwealth Ave.
- Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
Rear Façade and Back Alley
- Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
Upper Roof
- Work continues constructing the new mechanical penthouse and emergency electric room.
- Assembly and installation of the DOAS unit, piping, sheet metal ductwork, and electrical connections continue.

Tower B
- Staging crews will install and assemble scaffolding on the north, south, east, and west façades in preparation for the next phase of work.
West Podium Terrace
- Assembly and installation of heat pumps and condensers, including piping and electrical connections, continues on the mechanical platform.


Multipurpose Room Roof (Podium D)
- Work continues constructing the new boiler room.
Cummington Mall
(In and around the fenced area)
- Daily deliveries of tools, supplies, and materials will be received at the construction loading docks within the fenced area.
- Crews are assembling the four-post hoist way structure and bridge beams for Tower B.
- Two-car personnel and materials hoist way remains in operation.
- (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.)
- Tower B hoist way bridge construction is ongoing.
Cummington Mall West
- BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.
Hinsdale Mall
- Crews will be cleaning up and demobilizing equipment and fencing.
Commonwealth Ave.
- Crews will be cleaning up and demobilizing equipment and fencing.
Interior Work
Tower A
- Steel stud framing of interior partitions and soffits continues.
- Installation of hollow metal door frames continues.
- New window installation continues.
- Plaster patching at columns and beams continues.
- Installation of fire protection sprinkler risers, mains, branch lines, and heads continues.
- Rough-in of HVAC piping, electrical, fire alarm, plumbing, and sheet metal ductwork continues.

- Pressure testing of mechanical piping and sheet metal ductwork continues.
- Installation of structural steel clips, plates, kickers, and beam penetrations continues.
- Stair handrail and riser alterations are ongoing.

- Application of spray fireproofing, expanding foam insulation, and firestopping continues.
Parking Garage
- Electricians continue running wiring, conduits, and electrical gear throughout Levels 1–3.

- Plumbers continue installing new water and drain lines in the basement and Levels 1–3.
- Concrete and steel structural repairs continue on Levels 1–3.
- Sprinkler work continues on basement and Levels 1–3.
- Masons continue installing block walls in the new mechanical and electrical rooms.
- Please watch for adjusted parking patterns, cones, and observe signage.
During the week of 1/19
No work planned Monday, 1/19 | Crews working 1st & 2nd shifts
Exterior Work
Tower A
4th Floor Podium Roofs
- Low roofs will be used as laydown areas for tools, supplies, materials, and temporary heating units.

East & West Facades
- Crews will be working on the low roofs east and west of Tower A.
- Masons will continue exterior brick veneer restoration work.
- Installation of new windows and metal panels continues.

Front Façade and on Commonwealth Ave.
- Masons will continue exterior brick veneer restoration work.
- Installation of new windows and metal panels continues.
Rear Façade and Back Alley
- Masons will continue exterior brick veneer restoration work.
- Installation of new windows and metal panels continues.
Upper Roof
- Work continues constructing the mechanical penthouse and emergency electric room.
- Assembly and installation of DOAS units, piping, sheet metal ductwork, and electrical connections continue.

Tower B
- Scaffolding installation continues on all façades.

West Podium Terrace
- Assembly and installation of heat pumps and condensers continue.

Multipurpose Room Roof (Podium D)
- Work continues constructing the new boiler room.
Cummington Mall
(In and around the fenced area)
- Daily deliveries of tools, supplies, and materials will continue.
- Temporary elevator hoist way and bridge beam assembly for Tower B continues and impacts two entry/exit doors at 111 Cummington Mall.

Cummington Mall West / Hinsdale Mall
- BUPD detail officers and construction staff will be on-site.
Interior Work
Tower A
- Steel stud framing of interior partitions and soffits continues.
- Installation of hollow metal door frames continues.
- Drywall installation and taping continue.


- New window installation continues.
- Plaster patching continues.
- Sprinkler installation continues.
- Rough-in of MEP systems continue.
- Pressure testing continues.
- Stair alterations continue.
- Fireproofing and firestopping continues.
- Otis elevator modernization continues.
- Third-party inspectors remain onsite as needed.
Parking Garage
- Work continues in the main electrical room.
- Electrical bus duct riser installation for Tower A continues.

- Mechanical piping installation continues.
- Fuel storage room construction continues.
- Parking & Transportation office construction continues.
- Temporary heaters remain in operation on Level 3.
- Please watch for adjusted parking patterns, BUPD detail officers, cones, and observe signage.
Future / Notable Tasks
- Window leak testing on Tower A will continue.
- FM Global roof uplift testing will continue.
- Emergency generator crane lift onto the Tower A roof is scheduled for February 7.