Warren Towers Renovation – Construction Update – 12/13/2024

General Project Information

  • Daily works are from 7:00 am until 3:30 pm.
  • The team is currently in the enabling phase, crews on site are small, mainly working in the parking garage, rear alleyway, and in Cummington Mall.
  • Emergency Contacts
    • Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758 

During the weekend of 12/14

  • No work is planned for this weekend.
Temporary construction power shed.

During the week of 12/16

Exterior Work

Cummington Mall

  • Electrical work in and around the newly constructed power shed.
  • Painting of the temporary construction power shed.

Interior Work

Parking Garage

  • Working in the temporary plastic dust enclosures, crews will be chipping existing concrete fireproofing at the new steel connections on level 2.
  • Electrical work continues in the temporary electric room on the 1st floor.
Dust enclosures for removal of concrete fireproofing.

Future/Notable Tasks

  • Crane work is tentatively scheduled for the weekend of January 25th; more information will be provided.

View all posts