Warren Towers Renovation – Construction Update – 12/13/2024
General Project Information
- Daily works are from 7:00 am until 3:30 pm.
- The team is currently in the enabling phase, crews on site are small, mainly working in the parking garage, rear alleyway, and in Cummington Mall.
- Emergency Contacts
- Owners Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
- Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758
During the weekend of 12/14
- No work is planned for this weekend.
During the week of 12/16
Exterior Work
Cummington Mall
- Electrical work in and around the newly constructed power shed.
- Painting of the temporary construction power shed.
Interior Work
Parking Garage
- Working in the temporary plastic dust enclosures, crews will be chipping existing concrete fireproofing at the new steel connections on level 2.
- Electrical work continues in the temporary electric room on the 1st floor.
Future/Notable Tasks
- Crane work is tentatively scheduled for the weekend of January 25th; more information will be provided.