|
How
much will the new I-93 plan really help?
By
Max
Heuer
WASHINGTON,
Oct. 31, 2002--Whether traffic on Interstate 93 is going to
get better any time in the next decade is still anybody's
guess.
The
U.S. Department of Transportation formally announced Thursday
that the $420 million project to widen I-93 was one of several
construction projects put on an expedited list to speed up
environmental review. But exactly how much faster the process
will be still isn't clear.
"(In
terms of) how does (the program) actually get implemented
and what difference ultimately will it effect I don't know,"
Jeff Brillhart, director of project development for New Hampshire's
Transportation Department and the former manager of the I-93
project, said in a phone interview Thursday.
The
list is part of a program that -- under an executive order
from President Bush about six weeks ago- - will create a Cabinet-level,
interagency task force designed to simplify the environmental
review process without upsetting federal law on the issue.
Brillhart
said he hadn't seen any specific information on the task force
other than a press release. He said he was expecting that
eventually "something will come down from the Federal
Highway Administration."
The
goal behind the new task force is to avoid "duplication"
and "red tape" that have delayed projects, a U.S.
Transportation Department spokesman said Thursday on condition
of anonymity. Transportation Secretary Norman Mineta echoed
this statement in a press release, saying that "President
Bush asked his Cabinet to help states cut through federal
bureaucratic inertia to help them complete sound transportation
projects more quickly and at less cost."
The
department spokesman said that a "second wave" of
announcements is coming soon that will place other projects
around the country on the new list. The spokesman said that
the function of the new system was simply to avoid multiple
reviews of the same site by different groups with similar
interests.
The
Environmental Protection Agency has been involved for years
with the I-93 project, which would widen the highway lanes
in an 18-mile stretch between the Massachusetts border and
Manchester.
"(The
I-93 project) has been on a fast track basis
since day
one," said Elizabeth Higgins, Northeast director of the
EPA's Office of Environmental Review. Higgins said the widening
of I-93 was a "pilot project" for streamlining the
review process. Unlike with most construction projects, she
said, the I-93 project's environmental impact statement that
her agency made public Sept. 13 was preceded by months of
detailed interagency discussion.
But
the EPA and the New Hampshire Transportation Department have
been unable to come to a consensus on mitigating damage to
wetlands along the road - or on how much land in other areas
of the Granite State should be preserved in the place of wetlands
lost to the widening of I-93. This issue remains the single
biggest stumbling block between the two agencies.
Brillhart
said the EPA is pushing for secondary impact mitigation, which
would provide an additional 3,000 acres of land with high
ecological value. This land would be included because of the
potential for further loss of wetlands as a consequence of
an increase in business and housing development in New Hampshire
towns not directly adjacent to the highway, Brillhart said.
The
New Hampshire agency has agreed to 650 acres of wetland mitigation
for towns that are immediately adjacent to the highway, Brillhart
said. Higgins said the EPA had not specified an exact amount
of land, but that its position is that more land should be
included.
Brillhart
said that the New Hampshire Transportation Department does
not need EPA approval but added that there will be "some
negotiation" on the issue. The. Army Corps of Engineers,
the state Wetlands Bureau and the Federal Highway Administration
are the agencies that grant the the state highway agency permission
to widen the interstate, Brillhart said.
Brillhart
said that after environmental concerns are addressed, the
final design must be approved by these agencies. He estimated
that "some construction" would begin by 2004 but
that the project would probably not be completed until 2012.
Brillhart added that obtaining proper funding would be another
"critical item."
The
original estimate for the $ project was $150 million, state
transportation commissioner Carol Murray told The Union Leader
Wednesday. The department's budget is about $150 million a
year, and additional federal funding is "the other unknown"
in addition to the eventual cost of the project, Murray said.
Published in The
Manchester Union Leader, in New Hampshire.
|