Boston University: Student Village Phase II

Project Phases

Construction of the Student Village will consist of five phases spanning from January 2007, until May 2008.

  • Construction of the Foundation: The ground is cleared and the new foundation for the Student Village is laid. Completed.

  • Site Utilities: Installation of utilities will result in traffic disruptions on Harry Agganis Way and North Connector. Completed.

  • Steel Frame: Once the foundation is in place, workers will begin erecting the steel structural supports.

  • Building Exterior: Install exterior panels of terra cotta, metal and glass.

  • Building Interior: Interior finish work.