March 1 |
2 |
3 |
4 |
5 |
6 |
| 7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 MUBLCOM Unpacks |
18 MUBLCOM preps
|
19
TERRIERS Unpack |
20
Functional Test
|
21
Functional Test |
22
Functional/ MUBLCOM IVT
|
23
Funct & MUBLCOM IVT Review
|
24
Flight Sim. #3 |
25
Flight Sim. #3 Review |
26
MBLCM NEA Harness Removed
|
27
MBLCOM Harness Rework |
28 MBLCOM Harness Rework |
29
FTS Bat Inst/ MBLCOM Retest
|
30 FTS Bat Inst
|
31 Bat Inst/ MUBLCOM Harness Rework
|
April 1
Inst MBLCM Harness
|
2
MBLCM Mate TERR Pre-mate Review
|
3
TERRIERS Mate
|
4
Easter
|
5
Flight Sim. #4
|
6
Flight Sim. #4 Review/HAPS Pressurized
|
7
Install Ballast LN-100 Test |
8
LN-100 Operational Test
|
9
Stand Down
|
10
Stand Down
|
11
Stand Down
|
12
Stand Down
|
13
Stand Down
|
14
Stand Down
|
15
Delta Launch
|
16
Stand Down
|
17
Stand Down
|
18
Stand Down
|
19
Stand Down
|
20
Stand Down
|
21
Stand Down
|
22
Stand Down
|
23
Stand Down
|
24
|
25
|
26
|
27 Athena launch
|
28
|
29
|
30
|
May 1
|
2
|
3
|
4
MUBLCOM connector rework
|
5
Flight Sim #4a
|
6
Flight Sim #4a
|
7 Titan IV launch
LN-100 Op. test
|
8
|
9
|
10
Fairing Installation
|
11
Fairing Installation
|
12
Fairing Installation NASA LRR
|
13
L1011@VAFB Transfer to AIT
|
14
LMCM Launch Rehearsal FTS test
|
15
Transport and Mate to L1011
|
16
NASA FRR WR LRR
|
17
Launch 22:05:47- 22:14:26 PDT |
18
Backup Launch date
|
19
|
20
|
21
|
22
|