| Date |
Time |
Activity |
Activity Details/Status |
| 5-17-99 |
15:30 |
Pre-Launch |
The launch team has arrived at the hotpad.
The weather looks great and we are set for
launch!
|
| 5-16-99 |
15:00 |
Pre-Launch |
We attended the FRR and LRR. There appear to be
no holds for launch. WE ARE A GO FOR MAY 17!
|
| 5-15-99 |
14:00 |
Mate to L1011 |
TERRIERS is mated to the L1011. We performed a
simulated arming sequence to ring out the GSE and COM lines.
The spacecraft is now set and secure for countdown on launch day.
|
| 5-15-99 |
6:00 |
Transport |
Transport from Bldg. 1555 to the Hotpad has begun.
The L1011 arrived yesterday evening.
|
| 5-14-99 |
19:00 |
LMCM/Launch Rehersal/LPO Training |
The transfer to AIT was completed successfully and no issues
surfaced at the LRR yesterday. The L1011 work seems to be
coming along, so currently there are
no issues keeping us from a 5-17-99 launch. Today we
participated in the mission rahersal. It was informative,
and there were no outstanding TERRIERS issues. We ran the
disarming procedure with the LPOs to familarize them with
TERRIERS. Tim also attended this morning's LMCM in which
there were no outstanding TERRIERS related issues
|
| 5-13-99 |
08:00 |
Pre Transport |
Final touches on the fairing closeout continue.
We will transport the vehicle to the AIT today. A problem
with the L1011 was announced - horizontal stabilizer needs
to be replaced - so we may slip a day or two on launch.
|
| 5-12-99 |
09:45 |
Fairing Closeout |
Final touches on the fairing closeout continue.
We shipped out the secondary GS back to Boston and
we are preparing to support moving the vehicle onto the AIT
(transport trailer), tomorrow morning.
|
| 5-11-99 |
09:05 |
Fairing Closeout |
The fairing halves went on yesterday without any problems, and
it will be closed out today if we continue at our
current rate of progress.
The Titan has slipped, so barring any unforeseen problems, we
will launch on Monday May 17th!
|
| 5-10-99 |
07:55 |
Fairing Closeout |
This morning we will perform the fairing closeout procedures
on the satellite. We are still working towards a launch on the
17th, but have still not heard about the Titan. It is
reported
that the Titan problem was software, which may
indicate a need for them to slip futher. This would clear the
way for us to launch on the 17th.
|
| 5-7-99 |
07:45 |
Fairing Closeout |
Completed a spacecraft check yesterday - all looks good.
We also participated in a Pre-LRR and found that there
are still some issues with the vehicle that are being worked...
We expect a data go from Flight Sim #4a later this
morning, so we'll start fairing closeout then. The latest
on the launch date is that they will make the decision on
the Titan IV on Monday. There are rumors that the
Air Force and Lockheed may not be comfortable with
the 15th. In any case, it looks like it will only be a
couple of days slip if they push the Titan to the 15th...
|
| 5-6-99 |
08:30 |
Flt Sim #4a |
Flight Sim 4a was completed yesterday and all indications
are that it went well. The data is being processed today and
we expect a "data go" tomorrow. The bad news for today is that
the Titan IV wants to go on the 15th and they are talking to
NASA about it now. I believe this would be a 1 week slip for
us. We continue to work for a launch on the 17th, however.
|
| 5-5-99 |
08:30 |
Flt Sim #4a |
Flight Sim #4a to go off today. Also, the Air Force has give
us the 17th on the range. Furthermore, with the failure of the
Delta III last night, it looks like the GOES will be delayed.
The 17th looks very good for launch now!
|
| 5-4-99 |
08:00 |
Pre Flt Sim #4a |
Still no firm launch date has been scheduled, due to conflicts
with the GOES launch, and we are still working toward the 17th. The
MUBLCOM crew arrived this morning to work the dreaded NEA harness
and prepar e for Flight Sim. #4a - scheduled for tomorrow.
|
| 5-3-99 |
18:30 |
Post Anomaly |
No firm launch date has been scheduled, due to conflicts
with the GOES launch. We are still working toward the 17th. Flight Sim.
#4a is scheduled for Wednesday, and fairing closeout starting on Saturday.
Over the weekend we compiled a photo gallery page.
|
| 4-30-99 |
18:30 |
Post Anomaly |
Dan Cotton arrives to cover the next couple of
weeks. He checks in with the spacecraft. |
| 4-28-99 |
10:30 |
Post Anomaly |
OSC has received a verbal go-ahead and is waiting on written
confirmation to proceed with Flight Sim #4a on Wednesday. Our
launch date is still waiting for Range confirmation. We anticipate
it will be near May 17. Our working schedule,
based on this launch date, has been updated. Andy and
Sherri Stephan return to Boston. |
| 4-28-99 |
10:30 |
Standdown |
We are still waiting for an official go-ahead from NASA,
and Range confirmation of a launch date before OSC can
release a new schedule. |
| 4-28-99 |
10:30 |
Standdown |
We are still waiting for an official go-ahead from NASA,
and Range confirmation of a launch date before OSC can
release a new schedule. |
| 4-27-99 |
08:15 |
Standdown |
An error was found in a model was corrected it. Their model
now matches the OSC model. A scheduling meeting is planned for
later today to work out a new launch date. It is anticipated to
be around May 18. We will update the schedule when it becomes
available. |
| 4-26-99 |
08:10 |
Standdown |
TERRIERS is
mated to
Pegasus
and waiting for NASA and OSC simulations of the WIRE anomaly to
agree. We continue to trickle charge the power system. |
Our anticipated schedule has begun
to slide. We continue to trickle charge the power system.
| 4-23-99 |
09:00 |
Standdown |
TERRIERS is mated to Pegasus
and waiting for NASA and OSC simulations of the WIRE anomaly to
agree. Failure to come to agreement by today means we will
not be able to redo Flight Sim. 4 before Wednesday.
If it slips any further, it will begin to push the launch date.
We continue to trickle charge the power system.
|
| 4-22-99 |
08:40 |
Standdown |
TERRIERS is mated to Pegasus and waiting for NASA and OSC simulations
of the WIRE anomaly to
agree. We continue to trickle charge the power system. |
| 4-21-99 |
08:00 |
Standdown |
TERRIERS is mated to Pegasus
and waiting for NASA and OSC simulations of the WIRE anomaly to
agree. We continue to trickle charge the
power system. |
| 4-20-99 |
09:10 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from
NASA. We continue to trickle charge the power system.
We are anticipating 2 weeks to get NASA and OSC simulations
of the WIRE anomaly to agree. This will push the launch date
to the week of May 16. A true schedule has
not yet been determined. |
| 4-19-99 |
10:20 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from
NASA. We continue to trickle charge the power system. Our
earliest launch date appears to be May 12 based on range
availability, assuming Flight Sim 4 happens on Friday. |
| 4-18-99 |
10:20 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from
NASA. We continue to trickle charge the power system. |
| 4-17-99 |
12:00 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from
NASA. We continue to trickle charge the power system. |
| 4-16-99 |
15:00 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from
NASA. We continue to trickle charge the power system.
Our current best guess schedule will pick up with Flight Sim 4
being redone on Friday (April 23) at the earliest. |
| 4-15-99 |
13:45 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to
trickle charge the power system. The TERRIERS team watched the
Delta II carrying
Landsat 7 successfully
lift
off from (Space Launch Complex) SLC 2. Tim Cook and Valerie Taylor are returning
to Boston this evening to await resolution of the WIRE anomaly, and our new
launch date. |
| 4-14-99 |
17:00 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to
trickle charge the power system. Sherri Godlin Stephan arrived to supplement the
launch crew. |
| 4-13-99 |
16:54 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to trickle charge the power system. |
| 4-12-99 |
16:53 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to trickle charge the power system. NASA held a series of meetings today in which it was decided that we should not mate the fairing until after meeting again on Wednesday. The Wednesday meeting will allow NASA time to review data from several models which are currently being used to try to understand the yaw anomaly. As a result, it is not possible to launch before the 22nd of April. |
| 4-11-99 |
12:45 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to trickle charge the power system. On a more positive note, the leak in the roof is fixed. |
| 4-10-99 |
10:50 |
Standdown |
TERRIERS is mated to Pegasus and awaiting a go ahead from NASA. We continue to trickle charge the power system. |
| 4-9-99 |
18:19 |
Standdown |
We had started removing our protective covers in preparation for fairing installation when Orbital was instructed by NASA to standdown. NASA Goddard is concerned about a yaw event seen during the WIRE launch and has issued an "indefinite hold" until the issue is closed. No work will be performed on the vehicle until Monday when Orbital and NASA will regroup. The LRR Monday has been canceled and our April 18th launch date is in question. We have rebagged the spacecraft and are awaiting developments. |
| 4-8-99 |
09:50 |
Fairing Closeout |
We started our fairing closeout procedure. We have removed all test and RF GSE
and installed the final flight high voltage safety plug. Our next communication
with the spacecraft will be from orbit. |
| 4-7-99 |
20:09 |
Post-Mate Ops |
Today we finished up our final payload checkout and prepared for fairing
installation Thursday. All systems look good. |
| 4-6-99 |
08:30 |
Post-Mate Ops |
Today we started our post mate testing sequence. Testing was somewhat limited
because a series of hazardous vehicle operations to pressurize the RCS and HAPS
meant that we had to clear the high bay and leave the facility during those
operations. All indications are that the spacecraft is in good working order and
we should finish testing Wednesday. |
| 4-5-99 |
09:51 |
Post-Mate Ops |
TERRIERS successfully participated in flight sim #4 with no outstanding issues. |
| 4-4-99 |
16:30 |
Post-Mate Ops |
TERRIERS is mated to the Pegasus and awaiting flight sim #4. |
| 4-3-99 |
13:30 |
Mate Ops |
TERRIERS is mated successfully to the Pegasus. |
| 4-2-99 |
13:30 |
Pre-mate Ops |
We participate in the TERRIERS pre-mate review. It is accepted that that we have
been ready to mate for over a week, and that there are no liens against launch
from the TERRIERS spacecraft side. |
| 4-2-99 |
11:40 |
Pre-mate Ops |
A general email announcement implies incorrectly that TERRIERS caused launch
delays. THIS IS UNTRUE.
Integration has gone extremely well thus far and we are ready to mate.
It is a harness on OSC's MUBLCOM secondary satellite that has been holding up
integration for the past week along with the review of a vehicle anomaly on the
WIRE flight. In other news, we completed the tip maneuver of the satellite in
preparation for the mate. Operations were completed inside an hour while MUBLCOM
continues to check out their harness. |
| 4-1-99 |
10:40 |
Pre-mate Ops |
MUBLCOM's harness is due back today. The new launch date is still not completely
set, but it looks like it will be the 19th. They have stretched out the schedule
to accommodate the later date. See the updated schedule
. |
| 3-31-99 |
18:00 |
Pre-mate Ops |
MUBLCOM's harness went out to Pomona, CA for re-rework. OSC is requesting the
19th for a launch date from the range, but NASA is still pushing for the 17th.
This depends upon how willing the range is to reconfigure about 40 hours after
the planned Delta II on the 15th. The only operations we did besides battery
maintenance, were some flow gauge tests on our N2 purge system. They were
successful. |
| 3-30-99 |
18:00 |
Pre-mate Ops |
MUBLCOM's reworked harness failed initial tests and must be reworked again.
This will take 2 days and pushes TERRIERS mating operations till Friday or
Saturday. The launch date has slipped from the 12th to a later date which is
still TBD. We may get word tomorrow.... |
| 3-30-99 |
07:45 |
Pre-mate Ops |
OSC announced that the anomaly on WIRE's first stage has caused a software
change for the Pegasus avionics. This will cause a 2 or 3 day delay. They are
still looking at the 12th for a launch date, but it is much less likely now. We
heard a rumor of the 17th, due to the Delta on the 15th. Spacecraft mates will
continue as scheduled. |
| 3-29-99 |
18:00 |
Pre-mate Ops |
We performed an Alk. Battery test successfully. MUBLCOM's harness arrives
and is being installed. |
| 3-29-99 |
07:30 |
Pre-mate Ops |
MUBLCOM's harness is due to arrive around 18:00 and will be installed
tonight. Testing on the harness will take place tomorrow morning with mate to
commence mid morning. |
| 3-28-99 |
10:00 |
Pre-mate Ops |
TERRIERS battery maintenance operations continued and we verified our
recycle procedure. |
| 3-27-99 |
10:00 |
Pre-mate Ops |
Only TERRIERS battery maintenance operations were carried out today as we
await mate. |
| 3-26-99 |
18:00 |
Pre-mate Ops |
Only TERRIERS maintenance operations were carried out today as we await
mate. MUBLCOM's cabling discrepancy mitigation plan was completed and we are
holding our launch date of April 12th. MUBLCOM will send the affected harness
back to Dulles for rework over the weekend, reinstall and do testing on Monday,
and mate Tuesday. TERRIERS will then mate on Wednesday. In the mean time the
vehicle ops that were scheduled for Monday and Tuesday will go on as scheduled.
The result is we only lose a day which we will make up next Saturday. See updated schedule |
| 3-26-99 |
10:00 |
Pre-mate Hold |
The discrepancy in MUBLCOM's cabling is being reviewed and it appears that
we will not mate this weekend. The current plan is to install shielding on one
set of cables and mate MUBLCOM this afternoon. This would be followed by an
intermediate test to verify there is no cross talk. TERRIERS would then be mated
on Monday. This plan is currently being evaluated by NASA and OSC management.
|
| 3-25-99 |
14:00 |
Flt Sim #3 |
A discrepancy in MUBLCOM'S Non Explosive Actuator (NEA) cabling is announced
and is being worked. A mitigation action has been developed and will be
discussed with NASA tomorrow. This will probably delay MUBLCOM mate until late
Friday or early Saturday. We also successfully ran the full arming and recycle
procedures proofing a recycle mitigation procedure and the strip chart monitors.
|
| 3-25-99 |
08:00 |
Flt Sim #3 |
We verified that the recycle discrepancy was due to a design feature of the
power system and developed 3 mitigating procedures. Two of the 3 procedures are
tested. Also, we incorporated the strip chart monitors into the arming
procedure. |
| 3-24-99 |
18:15 |
Flt Sim #3 |
Flight sim #3 was set up all day and began around 18:15. The TERRIERS arming
sequence runs smoothly, but the spacecraft boots unexpectedly during the recycle
procedure. We have a working theory for the discrepancy and we will review the
events and schematics tomorrow. In any case, the discrepancy does NOT pose a
risk of radiation inside the fairing. |
| 3-24-99 |
08:00 |
Functional |
Functional data is reviewed. All the data checks out. |
| 3-23-99 |
17:00 |
Functional |
Functional test complete. Begin data review. |
| 3-23-99 |
08:00 |
Functional |
Completed verification of TESS E and GISSMO electronics. Obtained range
certification, so we can now radiate without getting clearance. In the afternoon
Paul Bernhardt verified CERTOs (radio beacon) functionality in both the stowed
and deployed configurations. |
| 3-22-99 |
08:00 |
Functional |
Waited for range clearance and then continued with instrument checkout. TESS
A-D electronics were verified. We also completed successfully an MSS phasing
test. Due to pulser cable problems, we were unable to complete TESS E/G. We hope
to finish on 3/23. Also Paul Bernhardt arrived and joined the team for CERTO
(radio beacon) checkouts, which we hope to complete on 3/23 as well. |
| 3-21-99 |
08:00 |
Functional |
Worked a GSE Tx problem all morning. After we fixed it, we tested the HCIs,
and started the instrument checkout. We also performed a beacon antenna
deployment test; everything continues to check out. |
| 3-20-99 |
08:00 |
Functional |
The remainder of the GSE is set up and we begin the post ship functional
tests. Various minor issues with the GSE are uncovered and worked. We complete
the low level functional - all checks out so far. |
| 3-19-99 |
17:00 |
Lift |
TERRIERS is lifted onto the workstand and placed in the clean room at
building 1555. |
| 3-19-99 |
09:00 |
Unpack |
TERRIERS arrives at Building 1555 and is unpacked. All indications show that
TERRIERS had a smooth ride. The GSE is unpacked and we start to set it
up. |
| 3-18-99 |
20:00 |
Travel |
The TERRIERS integration team (Tim Cook, Andy Stephan, Valerie Taylor, and
Dan Cotton) arrives in Lompoc.
|