Archives

Admissions Reception Center Construction Update 12-13-13

As we near completion of the new Admissions Reception Center (Owner move-in planned to begin January 7th) we anticipate removing the stockpiled soil from the CAS Parking Lot over the course of two days beginning next week Tuesday 12/17 (Changed from Monday 12/16) and continuing on into Wednesday 12/18. Attached is a plan diagram indicating […]

» Read More

Admissions Reception Center Construction Update 10-22-13

Starting today, Tuesday 10/22, our contractor will be temporarily storing some excavated soil in the area of the CAS Parking Lot shown on the attached diagram.  We plan to re-use this soil on site and hope to have it removed from this parking lot area as soon as possible, sometime between 2 and 4 weeks […]

» Read More

Admissions Reception Center Construction Update 10-8-13

The date for our final asphalt topping of the short section of Bay State Road from the Granby Street intersection up to and including the entry area of the CAS Parking Lot will be on Saturday November 2nd pending good weather…our fall back date should the weather turn against us would be the following Saturday […]

» Read More

Admissions Reception Center Construction Update 7-9-13

Beginning today, Tuesday July 9th, please see the attached revised work diagram. Our construction barrier is moving out a bit to the intersection of Granby street and we will begin pulverizing some of the existing asphalt paving behind the barrier. For questions please send an email to fmp@bu.edu  

» Read More

Admissions Reception Center Construction 4/5/13

Other than some brick and concrete sidewalk replacement where we had been trenching in the Alpert Mall area, and final replacement of the grass surface, we are essentially now complete with the major work of the Sewer Separation Project. The next three phases of construction in the roadway area of the new Admissions Reception Center […]

» Read More

Admissions Reception Center – Construction Activity 2/4/13

We are now moving on into Part 2 of the Sewer Separation Project that will install new storm line drainage piping in the Alpert Mall between the School of Social Work and the Marsh Chapel.  This work will continue for the next several weeks. As part of our renovation work for the new Admissions Reception […]

» Read More

Admissions Reception Center – Construction Activity 1/16/13

We have completed the work in the CAS Parking Lot, all of the earth mounds have been removed and the parking lot spaces have been re-striped.  The lot is now open for use by all permit holders and deliveries as per normal. We thank you for your patience! We will now be moving on to […]

» Read More

Admissions Reception Center – Construction Activity 1/7/13

  Attached, please find a photo of the current conditions and our diagram for the work that has been completed as of Friday 1/4. We are now approximately 60% complete with the CAS Parking Lot portion and at this point we are on track for a Tuesday 1/15 completion with the lot intended to be […]

» Read More

Admissions Reception Center – Intersession Construction Activity

1)     The CAS Parking Lot will be closed for vehicle access from Monday 12/24 through Monday 12/31.  Two construction crews will be working full-time in the lot to install the new sewer separation lines with equipment trucks, excavated earth, back-hoes, etc., to take advantage of the University closing to complete this work in the lot […]

» Read More

Admissions Reception Center – Construction Activity 12/11/12

Over the next week, the median strip of grass and granite curbs in the middle of George D. Hart Way will be removed and paved over with temporary asphalt paving.  During this period traffic will still flow on either side of the median and a police detail will be on site to help direct the […]

» Read More