News
Geothermal Well Drilling Initiative – Construction Update – 02/15/19
During the week of February 18: Parking Lot Test Well #1 Geothermal piping installation was completed on 2/12 and vertical deviation measurement of the bore hole was completed on 2/13. This week, starting on 2/22, the contractor will be running a 48-hour thermal conductivity test involving circulating fluid through the... More
Goldman School of Dental Medicine – Construction Update – 2/15/19
During the weekend of February 16: Starting at 5:30 p.m. Friday night, demolition and abatement will continue in the west connector space. On Saturday, crews will continue to remove formwork from the recently poured foundation walls at the two-story north addition. Also, on Saturday, in the newly renovated Student Admissions... More
Goldman School of Dental Medicine – Construction Update – 2/8/19
During the weekend of February 9: On Saturday, installation of rebar and formwork will continue on the foundation of the two-story addition (along the north side of GSDM). Also, on Saturday, crews will continue removing the precast concrete façade panels along the west elevation to allow for the connection of... More
Geothermal Well Drilling Initiative – Construction Update – 2/8/19
During the week of February 11: Parking Lot Test Well #1 The contractor Finished reaching target depth of 1500’ of the drilled hole on 2/5/19 This week the contractor will be installing geothermal piping and measuring verticality. Additionally, the geotechnical engineer will be obtaining soil samples from multiple locations in the... More
Goldman School of Dental Medicine – Construction Update – 2/1/19
During the weekend of February 2: On Saturday, installation of rebar and formwork will continue on the foundation of the two-story addition (along the north side of GSDM). Also, on Saturday, crews will continue removing the windows along the west elevation. This is the start of the total removal of... More
PMWeb is Now Live!
January 30, 2019 We are excited to announce that our new project management system, PMWeb, is now live! This new system is part of a multi-year strategic planning initiative designed to transform critical processes, clarify roles and responsibilities, and create a new organization structure that rolled out in October 2018 to... More
Goldman School of Dental Medicine – Construction Update – 1/25/19
During the weekend of January 26: On Saturday, installation of rebar and formwork will continue on the foundation of the two-story addition (along the north side of GSDM). Crews will also continue to run electrical conduits from the street into the new electrical room in the basement. Also, on... More
Goldman School of Dental Medicine – Construction Update – 1/18/19
During the weekend of January 19: On Saturday, installation of rebar and formwork will continue for the foundations of the two-story addition (along the north side of GSDM) and the seven-story addition (along the west side of GSDM). On Saturday, crews will be working in two shifts—day from 7... More
Goldman School of Dental Medicine – Construction Update – 1/11/19
During the weekend of January 12: On Saturday, installation of rebar and formwork for the foundation of the two-story addition (along the north side of GSDM) will continue. Crews will also be installing a hot-applied waterproofing system on the new receiving area foundation walls. The heating equipment required for this... More