Archives

New Balance Field Construction Activity for the Period of May 20 – May 25

Anticipated construction activities for the week of May 20 – May 25: *The contractor will NOT be working on Saturday, 5/18/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the equipment, and [...]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of May 20 – May 24

Anticipated construction activities for the week of May 20 – May 24: 1. 744 Commonwealth Ave – The contractor will install the steel reinforcing bars for the new concrete floor. The concrete floor is tentatively scheduled to be poured on Friday, May 24. 2. 750 Commonwealth Ave – The contractor will be performing the following [...]

» Read More

New Balance Field Construction Activity for the Period of May 13 – May 17

Anticipated construction activities for the week of May 13 – May 17: *The contractor will NOT be working on Saturday, 5/14/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the equipment, and [...]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of May 13 – May 17

Anticipated construction activities for the week of May 13 – May 17: **The Contractor will be working the day shift (7:30am – 3:30pm) beginning Monday, May 13 and continuing through the start of classes in September** 1. Abatement – The abatement work on the first floor of 750 Comm Ave is complete. Select additional abatement [...]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of May 6 – May 10

Anticipated construction activities for the week of May 6 – May 10: 1. Abatement – The contractor will continue to abate the ceiling on the first floor of 750 Comm Ave. (the old Guitar Center space). It is anticipated that the abatement will finish by the middle of the week. 2. Mechanical/Electrical/Plumbing – The contractor [...]

» Read More

New Balance Field Construction Activity for the Period of May 6 – May 10

Anticipated construction activities for the week of May 6 – May 10: *The contractor WILL be working on Saturday, 5/4/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the equipment, and construction [...]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of April 29 – May 3

Anticipated construction activities for the week of April 29 – May 3: 1. Site Work – The contractor will be installing insulation and a vapor barrier on the floor of the 744 Comm Ave garage in preparation for pouring the new concrete slab. 2. Abatement – The contractor will continue to abate the ceiling on [...]

» Read More

New Balance Field Construction Activity for the Period of April 29 – May 4

Anticipated construction activities for the week of April 29 – May 4: *The contractor will not be working on Saturday, 4/27/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the equipment, and [...]

» Read More

Sumner M. Redstone Building Groundbreaking Set for April 19

Celebration will mark official start of long-awaited construction project for School of Law Boston University School of Law will hold the groundbreaking ceremony for the Sumner M. Redstone Building and Law Tower renovation, the centerpiece of the School of Law’s Campus Campaign, on Friday, April 19 at 2:30 pm on Alpert Mall in front of [...]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of April 15 – April 19

Anticipated construction activities for the week of April 15 – April 19: 1. Site Work – The contractor has completed the installation of the new utility pipes that will go under the slab. They will be leveling the ground elevation to prepare for the new concrete slab. 2. Abatement – The contractor will begin the [...]

» Read More