Admissions Reception Center Construction Update 12-13-13

As we near completion of the new Admissions Reception Center (Owner move-in planned to begin January 7th) we anticipate removing the stockpiled soil from the CAS Parking Lot over the course of two days beginning next week Tuesday 12/17 (Changed from Monday 12/16) and continuing on into Wednesday 12/18. Attached is a plan diagram indicating […]

» Read More

Admissions Reception Center Construction Update 10-22-13

Starting today, Tuesday 10/22, our contractor will be temporarily storing some excavated soil in the area of the CAS Parking Lot shown on the attached diagram.  We plan to re-use this soil on site and hope to have it removed from this parking lot area as soon as possible, sometime between 2 and 4 weeks […]

» Read More

Admissions Reception Center Construction Update 10-8-13

The date for our final asphalt topping of the short section of Bay State Road from the Granby Street intersection up to and including the entry area of the CAS Parking Lot will be on Saturday November 2nd pending good weather…our fall back date should the weather turn against us would be the following Saturday […]

» Read More

New Balance Field Construction Update – Gardner Street Traffic

Please be advised that with the completion of the New Balance Field project, Gardner Street has returned to being open to two-way traffic between Babcock and Alcorn Streets.  The main entrance and exit to the garage is off of Gardner Street, down by the corner of Alcorn Street.  The intent is for those who will […]

» Read More

Admissions Reception Center Construction Update 9-24-13

As we near completion of the new Admissions Reception Center at the end of the year, we are now getting ready to pave the re-configured roadway from the corner of Granby Street up to and including the new entrance to the CAS Parking Lot. We have thought about how we could minimize impact on the […]

» Read More

Admissions Reception Center Construction Update 7-9-13

Beginning today, Tuesday July 9th, please see the attached revised work diagram. Our construction barrier is moving out a bit to the intersection of Granby street and we will begin pulverizing some of the existing asphalt paving behind the barrier. For questions please send an email to fmp@bu.edu  

» Read More

Engineering Product Innovation Center Construction Activity for the Period of July 8 – July 12

Anticipated construction activities for the week of July 8 – July 12: 1. 744 Commonwealth Ave – The contractor will be performing the following activities: a. Continue to close up the new walls and begin drywall taping b. Install new overhead ductwork c. Begin concrete floor polishing d. On the roof, the contractor will continue […]

» Read More

New Balance Field Construction Activity for the Period of July 8 – July 13

Anticipated construction activities for the week of July 8 – July 13: 1. Site & Utility Work: Already underway and continuing for the next couple of weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the equipment, and construction traffic in the form of dump trucks […]

» Read More

Engineering Product Innovation Center Construction Activity for the Period of June 17 – June 24

Anticipated construction activities for the week of June 17 – June 21: 1. 744 Commonwealth Ave – The contractor will be performing the following activities: a. Continue to frame the walls and construct on the new ramp that will connect building 744 Comm and 750 Comm b. Continue to install the new electric wiring c. […]

» Read More

New Balance Field Construction Activity for the Period of June 17 – June 22

Anticipated construction activities for the week of June 17 – June 22: *The contractor will be working on Saturday, 6/15/2013 and Sunday 6/16/2013 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from the […]