Myles Standish Hall – Construction Update – 6/22/18
For 6/23/18 to 6/29/18:
Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.
On-site Construction
Saturday Work – 6/23/18 – 7 am to 5 pm
- Clean up and load out
- Interior work – Myles
- Annex interior framing and MEP roughs
- Annex exterior façade work
Myles – 7 am to 6 pm
Demolition / Load Out
- Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps
Site
- Myles
- Beacon Street – Continue sidewalk and underground demo
- Point Park & Bay State Road
- Continue installation of pavers and landscape
Annex – 7 am to 6 pm
Demolition / Load Out
- Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps
Roof
- Masonry restoration
- Roof terminations, flashings, and masonry
Masonry Restoration
- Beacon Street & Raleigh Street – Continue with façade restoration