Myles Standish Hall – Construction Update – 6/22/18

 Myles Standish Hall - Construction Update - 6/22/18  Myles Standish Hall - Construction Update - 6/22/18

For 6/23/18 to 6/29/18:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

On-site Construction

Saturday Work – 6/23/18 – 7 am to 5 pm

  • Clean up and load out
  • Interior work – Myles
  • Annex interior framing and MEP roughs
  • Annex exterior façade work

Myles – 7 am to 6 pm

Demolition / Load Out

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpsters with ongoing daily dumpster swaps

Site

  • Myles
    • Beacon Street – Continue sidewalk and underground demo
  • Point Park & Bay State Road
    • Continue installation of pavers and landscape

Annex – 7 am to 6 pm

Demolition / Load Out

  • Load out Bay State Road and Raleigh Street with chute to dumpsters with ongoing daily dumpster swaps

Roof

  • Masonry restoration
  • Roof terminations, flashings, and masonry

Masonry Restoration

  • Beacon Street & Raleigh Street – Continue with façade restoration