Myles Standish Hall – Construction Activity – 07/16/16 to 07/22/16

For  07/16/16 to 07/22/16:

Deliveries

  • Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.

 Onsite Construction

Saturday 07/16/16 – Working 7 a.m. –  4 p.m.

Permission and permitting have been secured from the City to work from 7 a.m. to 4 p.m.

  • Demolition throughout building – Interior
  • Load out of dumpsters on the Beacon Street side of the building – Dumpster will be swapped throughout the day.
  • Activities will require trucks and equipment in the point park area – Access from Bay State Road will be required for dumpsters and equipment.
  • Installation of steel in the Annex alley between Myles and the Annex on the Bay State Road side of building.

Man and Material Hoist Construction

  • Concrete masonry unit (CMU) block infills around gates at all floors.
  • Constructing wood loading dock around perimeter of hoist base.

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Continue with load out down chute – Interior
  • Demolition and load out of basement
  • Abatement on floors 4, 5, and 6 – Interior
  • Demolition of floors 7 and 8 – Interior
  • Continue with demolition of existing freight elevator and floors 2 and 3 – Interior

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue installation of CMU at 9th floor on the Bay State Road side of the building.
  • Continue with masonry facade demo on the Beacon Street side of the building at 9th floor.
  • Continue with masonry demo on swing above the Annex.
  • Start installation of relieving angles on the Bay State Road side of building.

 Roof (Exterior)

  • Continue with layout and installation of CMU at parapet on the Bay State Road side of the building.

Alley Between Annex and Myles at Bay State Road

    • Installation of steel for transformer pad.
    • Start forming for concrete at transformer pad and squash court in basement.
    • Site work – Bring drain line in off of Bay State Road and then into the alley.
    • Alley underground electrical and drainage

Myles 7/14/16 Myles 7/14/16

For questions, please contact Brian Kelley.