For May 5  through May 19  you may expect:

The tarp system, which enclosed the building for work during the winter, will continue to be incrementally removed over the next few weeks as exterior walls are finished. Installation of flooring is ongoing. The installation of the masonry façade and back-up components continues and once finished will result in a reduction of the noise from within the construction project site.  Scaffolding on the north side of the building is being removed. When the scaffolding and tarp systems are completely removed, the facade and glass system will be significantly advanced and will serve as a barrier for keeping the sound within the project site. The team of 200 + people working on site every day is working hard to make sure the schedule is met.