News Archives

100 Bay State Road – Construction Activity for the period April 28 – May 12

Dear Colleagues & Neighbors: For April 28  through May 12  you may expect: The tarp system, which enclosed the building for work during the winter, will continue to be incrementally removed over the next few weeks as exterior walls are finished. Installation of flooring is ongoing. The installation of the masonry façade and back-up components […]

» Read More

Fire Alarm Inspection 4/30/2012 – 5/4/2012

4/30/2012 Testing from 7:00am – 3:00pm 648, 650, 654, 656 Beacon Street 533-541 Commonwealth Avenue 5/1/2012 Testing from 7:00am – 3:00pm 32 Harry Agganis Way 735, 949, 985 Commonwealth Avenue 11-19 Deerfield Street 115 Cummington Street 5/2/2012 Testing from 7:00am – 3:00pm 617, 619, 621 Commonwealth Avenue 512 Beacon Street (testing units only from 1st […]

» Read More

Underground Oil Tanks Being Removed

Underground oil tanks across campus are being removed as building heating systems convert from oil to gas.

» Read More

Fire alarm Inspection 4/23/2012 – 4/27/2012

4/23/2012 Testing from 7:00am – 3:00pm 273 , 275 , 300 Babcock st.   4/24/2012 Testing from 7:00am – 3:00pm 100, 120 Ashford st 277, 285, 278 Babcock st.   4/25/2012 Testing from 7:00am – 3:00pm 10 Buick st. ( testing bsmt, 1st , 2nd, 3rd, 4th and 5th fl)   4/26/2012 Testing from 7:00am […]

» Read More

100 Bay State Road – Construction Activity for the period April 14 – April 28

Dear Colleagues & Neighbors: For April 14  through April 28  you may expect: The tarp system, which enclosed the building for work during the winter, will be incrementally removed over the next few weeks as exterior walls are finished. Beginning the week of April 1st flooring installation will begin. The installation of the masonry façade […]

» Read More

Fire Alarm Inspection 04/16/2012 – 04/20/2012

04/16/2012 Testing from 7:00am – 3:00pm 53, 67, 141, 143, 145, 147 Bay State Rd.   04/17/2012 Testing from 7:00am – 3:00pm 602, 704, 708, 710, 714, 718 Commonwealth Ave. 135 Bay State Rd. pretest w/ Crocker Electric   04/18/2012 Testing from 7:00am – 3:00pm 722, 726, 728, 1019 Commonwealth Ave.   4/19/2012 Testing Testing […]

» Read More

100 Bay State Road – Construction Activity for the period April 7 – April 21

Dear Colleagues & Neighbors: For April 7 through April 21  you may expect: The tarp system, which enclosed the building for work during the winter, will be incrementally removed over the next few weeks as exterior walls are finished. Beginning the week of April 1st flooring installation will begin. The installation of the masonry façade […]

» Read More

Fire alarm inspection 04/09/2012 – 04/13/2012

  4/9/2012 Testing all units and comm area from 7:00am – 3:00pm 35, 37, 39, 41, 43 Buswell St.   4/10/2012 Testing all units and comm area from 7:00am – 3:00pm 252, 254, 258, 264 Huntington Ave 1 University Rd. 619 Memorial Dr.   4/11/2012 Testing all units and comm area from 7:00am – 3:00pm […]

» Read More