POWER OUTAGE ( MARCH 10 – MARCH 17 ) GSU – MUGAR – THEOLOGY – CENTRAL HEAT PLANT – TSAI CENTER -STONE SCIENCE – CAS LAW SCHOOL
This is to notify you that there are planned power outages scheduled for the week of spring break (March 10 – March 17).
The affected building list and outage schedule are detailed below. Please review this information and make sure all computers, etc. are appropriately shut down/turned off during the specified time frames.
This planned work is being coordinated by FM&P, and if you have any questions or concerns, please do not hesitate to contact me via the electrical department at (617) 353-9154.
Thank you for your cooperation as we work on electrical infrastructure upgrades.
Monday, March 12th
6:00AM – 7:00AM
-Building circuits currently on Line 2 will be switched to Line 1 and will affect the following buildings:
Each building will be interrupted for 30-45 minutes.
TSAI Center
Stone Science
CAS-1
CAS-2
Note: Buildings currently on Line 1 will not be affected.
8:00PM-12:00PM
There will be loss of power at the CAS-1 substation during this period
Tuesday, March 13th
6:00AM – 8:00AM
-Building circuits currently on Line 1 will be switched to Line 2 and will affect the following buildings:
Each building will be interrupted for 30-45 minutes.
TSAI Center
Stone Science
CAS-1
CAS-2
GSU
Mugar
Theology
Central Heat Plant & Law School
Thursday, March 15th 6:30PM – 7:00PM A momentary outage of CAS-1 switchboards will be experienced.
Friday, March 16th
6:00AM-8:00AM
Building circuits currently on Line 2 will be switched to Line 1 and will affect the following buildings:
Each building will be interrupted for 30-45 minutes.
TSAI Center
Stone Science
CAS-1
CAS-2
GSU
Mugar
Theology
Central Heat Plant & Law School
7:30AM-8:00AM
GSU
Mugar
Theology
Central Heat Plant & Law School
Each building will be interrupted for 30-45 minutes.