Jul 24, 2008
Electrical contractor will work on Level 7
Construction will take place Saturday, August 26, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Controls contractor will work on all... Read More...
-
Jul 18, 2008
Controls contractor and painter will work on all levels
Construction will take place Saturday, July 19, 2008 between the hours of 7:00 a.m. and 4:30 p.m. Controls contractor and painter will work on all... Read More...
-
Jul 10, 2008
Painter will work on Levels 2 and 5
Construction will take place Saturday, July 11 and Sunday, July, 12, 2008 between the hours of 7:00 a.m. and 4:30 p.m. On Saturday, the... Read More...
-
Jun 27, 2008
Telephone/Data systems contractor will work on Level 1
Construction will take place Saturday, June 28, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Telephone/Data systems contractor will work on... Read More...
-
Jun 20, 2008
Site contractor will work on grading
Construction will take place Saturday, June 21, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Electrical contractor and building management team... Read More...
-
Jun 12, 2008
Casework installer will work on Level 5
Construction will take place Saturday, June 14, 2008 between the hours of 7:00 a.m. and 4:00 p.m. Building automation and electrical work will take... Read More...
-
Jun 06, 2008
Electrical contractor will work on all floors
Construction will take place Saturday, June 7, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Concrete contactor will work on Level... Read More...
-
May 30, 2008
Concrete contractor will work on Level 1
Construction will take place Saturday, May 31, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Controls contactor will work on all levels.... Read More...
-
May 23, 2008
Paint contractor will paint Stair #2
Construction will take place Saturday, May 24, 2008 between the hours of 7:00 a.m. an 4:30 p.m. The paint contractor will paint Stair #2.... Read More...
-
May 16, 2008
Interior electrical work will take place on Levels 4, 5, 6 and 7
Construction will take place Saturday, May 17, 2008 between the hours of 7:00 a.m. and 4:00 p.m. Interior electrical work will take place on Levels... Read More...