|
The vast amount of the bulk soil (85%) excavation has been
completed. The earth retaining system is also mostly installed.
The concrete foundation system is currently
being installed in the southeast corner of the project site.
This activity is progressing from that area towards the north
and west.
It is anticipated that the structural steel
for the project will begin to arrive on site and be erected
sometime in early to mid December 2002.
Utility work is currently taking place
in the westbound parking lane of Commonwealth Avenue, east
of the project site. It is anticipated that this work will
be complete the week of November 18, 2002.
Arena Construction Progress: Initial
site mobilization started on May 21, 2002. The demolition
of the stand-alone administration building was started on
June 13, 2002.
|